Selected 2010-11 renovation projects at OVL
(for a more complete list of past projects and at other sites see below)
During the winter season WMRS staff carry out renovation and maintenance projects at OVL, depending on time and availability of funds. Below are examples of projects carried out in the winter of 2010-11. click on photos to enlarge
With the help of CDF inmate crews, we cleared about 1000' of perimeter brush. 3/18/11 This greatly aids in protection of the OVL facilities in event of a brush fire. 3-18-11
New sealed heat pump A/C system for Manis Lab. This high-efficiency system allows the lab to be better sealed against dust entry. 3-18-11 We replaced the old ceiling registers for the A/C systems in the Main dining hall, Dorms 1, and Dorms 2-5. The old registers obstructed the flow and reduced system efficiency. 3-18-11
We cleaned and renovated the OVL shop, including a new electrical breaker panel, new wiring, new overhead lighting, and new shelving for building supplies. Most building supplies not in immediate use were relocated to the storage locker facility (see right for example). 3/18/11

Electrical supply storage locker (#14 in storage locker facility) was organized and cleaned up. Smaller supplies were organized in plastic boxes to keep out dust and moisture since many storage lockers are not completely waterproof. 3-18-11

Storage locker facility from the north. One purpose of the facility is parking vehicles and equipment. We cleared out more spaces for this purpose. 3-18-11 Central aisle of the north locker facility - we built a storage area for plywood, doors, long boards, pipes and other building supplies. This area can now be used as a covered work space. 3-18-11
Storage locker facility as seen from the SW. The facility has two parts, north (including lockers 1-10) and south (lockers 11-20) We newly installed electrical outlets running along the base of the curved roof on both sides of the north aisle, along with two new 240V outlets, one in each facility, and a new electrical breaker panel. We found a semi-buried water tap at the facility that we plan to preplace with a freeze-proof hydrant.
We cleaned out the 14' high locker facility central aisles. They are tall enough to accommodate the snowcat and other large items. 3-18-11 We resurfaced and repainted the exterior of Dorm 1 in December-January. 3-21-11. The interior was re-done in previous winters and the new A/C system (at right in photo) installed in 2007.
We trimmed many OVL cottonwood trees, including hiring out this hazardous situation over the Geology trailer. Our staff trimmed several other trees. 3-18-11 2011 We completely replaced the hot and cold water supply plumbing in the Pace lab (the main quonset building). It is now much easier to drain for winter shutdown, and the water is much cleaner so that fixtures don't clog up.
 
We replaced the south facing windows on the Pace Lab with modern windows. We also redesigned the shutter system.  
   
   
   

List of renovation projects since 2003 - WMRS
Progress made as staff time and budget allow

OVL
Manis Lab front room re-floor 2003
Dining Hall refloor 2004
7 new Picnic Tables 2004
Dorm 1 interior renovation and refloor 2005
Dorm 2-4 bathroom renovation and interior paint 2008
New HVAC system for Dining Hall 2006
New HVAC system for Dorm 1 2007
New HVAC system for Dorm 2-5 2007
Install climate controlled greenhouse 2008
New Heat Pump system for Manis Lab 2010
Renovate Researcher Kitchen - new appliances, interior paint 2009
Install compact flourescent fixtures in offices 2008
New LCD projector and microphone system for south classroom 2010
Renovated, repainted Dorm 5 2010
Renovate Long-term Researcher Trailer 2010

COMPLETED OR IN PROGRESS 2011
Repaint Dorm 1 exterior, repair doors COMPLETED
Carpeted and cleaned VIP east COMPLETED
Renovated OVL shop w/ new wiring, breaker panel, new lights, cleaned and organized COMPLETED
Cleaned and renovated storage locker facility and shop storage lockers, new electrical outlets COMPLETED
Demolished and hauled away "grey whale" trailer COMPLETED
Hazardous tree rimming and removal around buildings COMPLETED
Fire break clearance around perimeter fence east half COMPLETED
Replace snowcat tracks and drive sprockets COMPLETED
Re-tile Manis Lab 90% COMPLETED
Install heat pump units in Manis Lab COMPLETED
Renovated and repainted 2 bathroom trailers (6 shower/toilet/sink units) COMPLETED
Lawn sprinkler and well repairs COMPLETED
Replace ice machine
COMPLETED
Re-plumbed Dorm 1, North Classroom, for water draining and winter shutdown IN PROGRESS
Re-keyed locks on Dorm 2-5, shop and other facilities for grreater security IN PROGRESS

CROOKED CREEK
Log painting - wood preservative, all log structures 2005
Trim painting doors and windows 2004-07
Shower replacement 2006-07
Lab reorganizing and refitting 2006-08
Landscaping - native plant garden 2007-09
Critical Loads power system 2009
Hughes Net satelllite internet service 2008
Completely retrofit Tellular phone installation 2010 COMPLETED
Clean out and retrofit storage quonset IN PROGRESS
Repaint logs with wood preservative 80% COMPLETED
Sheep pen upgrade
(funded by LLU) COMPLETED

BARCROFT
WM Energy Project off-grid power system 2008
Retrofit electrical distribution system to outbuildings 2006
Replace Pace Lab solar panels 2010
New chest freezer and kitchen refrigerator 2009
Starband Satellite Internet replacement 2009
Sheep pen upgrade (funded by LLU) COMPLETED
Pace Lab window replacement and new shutter design 90% COMPLETED

Remount Starband satellite dish on stable platform COMPLETED
Replace domestic water supply plumbing in entire Pace Lab COMPLETED

SUMMIT LAB
Minor renovation 2005
Clean-up after vandalism 2008
Electrical system upgrade PLANNED 2012 (outside funded)
Replace T1 antenna PLANNED 2012